Timeline of the investment
The construction of the T3 project will be executed in two phases. In a first phase, the consortium of the companies Budimex and DEME will build the 36 hectare terminal area next to Terminal 1. This new terminal area, which will be completed by the first half of 2024, will be entirely reclaimed from the sea. It will increase the handling capacity of Baltic Hub by 1.5 million TEUs (20-foot containers) to 4.5 million TEUs per year. In the second phase construction of the 717-meter-long, 17.5 meter deep quay wall will commence. This is scheduled to start in early 2023 and completed in the second quarter of 2025.
The T3 project also involves the purchase of seven quay cranes that are capable of handling the world’s largest vessels, as well as 20 semi-automated Rail Mounted Gantry (RMG) cranes for the container yard, which operators will be able to control remotely from ergonomically-designed workspaces. This will allow for a safer, efficient, modern and more comfortable working environment 365 days of the year.
New opportunities of T3
Baltic Hub is Poland’s largest container terminal and has experienced exponential growth from having just one deep-water quay and a capacity of 500,000 TEUs when it was founded 15 years ago, to becoming a true ‘Baltic Hub’ with two deepsea quays that handled more than 2.09 million TEUs in 2021 with a total annual capacity of up to 3 million TEUs. At this time, Baltic Hub has 1,300 meters of quay, 14 Ship-to-Shore (STS) cranes and an annual capacity of 2.7 MTEUs.
“Just 10 years ago, Poland was not a significant player in container handling”, said Marek Gróbarczyk, Secretary of State in the Ministry of Infrastructure, Government Plenipotentiary for Maritime Economy. Today, we are starting a historic investment - the largest container port. I think that the Management Board of Baltic Hub has not yet said the last word as their plans are very ambitious.
In addition, Baltic Hub has become a transport gateway to Central and Eastern Europe, with inland destinations such as the Czech Republic, Slovakia, Hungary and Germany. This is a result of continuous investments over the years, that elevated its rail capacity to 750,000 TEUs in 2020.
Baltic Hub CEO Charles Baker promises that Baltic Hub and its partners will carry out the project with the highest environmental standards right from the planning stage:
"Baltic Hub is a true 21st century terminal, and the T3 development will bring the latest low-carbon technology which any European port would be proud of. We emphasize once again that we are taking internationally recognized precautionary measures to protect the environment, marine life and habitats in the project area. This construction from A to Z will reflect our commitment to sustainable investments, for example through the use of low-carbon concrete and the deployment of low-emission equipment - such as electric yard cranes."
Baker adds that: “T3 will further enrich the services that Baltic Hub offers. Moreover, we will be able to attract new services, destinations and shipping alliances. By developing additional transshipment capacity and opening up new sea connections, we will also provide a boost to the Polish economy as a whole.”
The importance of the investment is also emphasized by Łukasz Greinke, the President of the Port of Gdansk.
“We are witnessing another milestone. After a long investor selection procedure, we selected DCT Gdańsk (today Baltic Hub) as the entity that submitted the most advantageous offer. Today we are moving to the next stage – the investment is being commenced. We keep our fingers crossed, wish you good luck and assure you of support at every investment stage. I hope that in two years we will meet at the ceremonial opening of another quay.”Poland will be 36ha bigger
The commencement of construction works at the new T3 Baltic Hub terminal completes the stage of work on executive designs and preparation of the construction site. These activities have been carried out as part of the so-called "early start" since the Budimex - Deme consortium signed the contract in July 2022. Now the consortium is starting works on the construction of a new terminal. The dredging of the sea route to the new terminal and the reclamation works under its basic structure begins. These works will be carried out, among others, by a special dredging ship and using the appropriate material from the bottom of the sea to construct a platform that will form the base of the new terminal. In addition, the consortium begins to build tight walls around the future terminal.
"We have completed the design and preparatory work. Its time of commencement for basic works on the construction of T3 Baltic Hub. In the coming months, we will expand the land territory of the Polish by 36 hectares. We have exceptional experience in the field of hydrotechnical works at the largest investments in the country. We will use this knowledge and experience of our engineers together with the equipment in the construction of the new terminal. The construction works themselves assume the execution of excavation works with a cubic capacity of over 4 million m3, the construction of a mooring line with a length of over 700 m. The T3 terminal itself will have an area of over 360,000 m2, an operational depth of 17 m and will be semi-automatic, which is a novelty in Poland and a trend currently present in the world”, says Cezary Łysenko, Director of the Infrastructure Construction Division of Budimex SA.
Laurent Closset, Regional Director for Northern Europe at DEME adds: "We are proud to be helping to build this terminal where we will carry out dredging and land reclamation work. We look forward to working with our partner in the consortium, Budimex, to combine our expertise to contribute to the implementation of ambitious development plans of the Baltic Hub”.