Maintenance works at BHCT Rail Siding
2025-11-27

Dear All,

 

We would like to inform you that on 8–13 December 2025 (week 50), due to maintenance works on crane rails on the BHCT siding,  following restrictions will be introduced:

 

  1. The length of the railway terminal tracks will be periodically decreased and increased as the work progresses.

  2. During this period, the trains will be splitted. The necessity of splitting the train and the exact parameters of the split will be determined each time between the shunting teams and the BHCT Railway Office and the Switchman and will vary on specific days, depending on the contractor's schedule of work.

  3. The completion of the works is planned for 13.12.2025 and the return to full operational length on 14.12.2025, 06:00 AM

 

Ad hoc window approvals and fixed window calendar will be adapted to operational capabilities and discussed individually with Train Operators.

We ask you to efficiently substitute and collect trains to avoid downtime, and the shunting teams to follow the recommendations of the BHCT Railway Office and the BHCT Switchman.

No additional works will be carried out on the actual siding rail tracks, so there will be no difficulties in shunting maneuvers.

We apologize for any inconvenience and  we shall make every possible effort to minimize the impact of restrictions on your work.