Completion of the relocation of the ARMG overhead cranes and the next stages of the T3 development
2026-07-23

Dear Sir or Madam,

We are pleased to announce the successful completion of the relocation of the ARMG cranes at Terminal T3 at the Baltic Hub, which enables the further commissioning of the new terminal infrastructure.

Lines 6 and 7 will be made available:

  • Week 30 – the blocks of Line 7 will be brought into operation,

  • Week 31 – the blocks on Line 6 will be brought into operation.

At the same time, over the coming weeks, work will be carried out in selected sectors at T3 to connect the storage blocks.

Technical acceptance checks, equipment tests and safety system tests relating to the work on Lines 1–5 will take place.

Due to the ongoing works, there may be temporary restrictions on access to selected terminal blocks at T3 and to the containers located within their premises.

Detailed information regarding the scope and dates of the restrictions will be provided in subsequent announcements.

Baltic Hub Container Terminal Sp. z o.o.