We are pleased to announce that the first four Ship to Shore cranes safely arrived and being offloaded on T3 Main Quay Wall. Currently they are under testing and completion of appropriate equipment, to be fully operational from March 2025. The next three STS already have started their journey from China and to arrive to Gdańsk in March 2025. 8 out of 20 RMG is already erected and 4 of them connected to the power and commissioned.
On the Main Quay Wall installation of furniture is continued. By the end of November most of the fenders and bollards were installed along with rescue equipment and navigation lights. Construction of CRMG beams was finished in six sections and container plinths are under construction. By the end of November, all twenty reefer racks had been assembled. Also, Contractor continued rail positioning, welding, hole drilling, installing chemical anchors for rail mounting systems, and installing rail mounting systems and grouting.
Power was applied to all the buildings and two fire tanks were assembled and filled with water. Engineer issued Taking Over Certificate for sections A, B, C, D and beginning of December Baltic Hub was issued first Usage Permit which allows to store empty containers on appointed container stacks.